Budget Allocation for Schedule Tribe Schools 2017-18

      2017-18   as on 31.12.2017
Scheme Head of A/c Opening Balance as on 01.04.17 Budget allocation Total fund aviable Releases (up to 3rd Qtr) Amount Received By KREIS

Expen diture

Balance

BedgetBC

BudgetSC

ST School Construction MDRS 4225-02-277-2-03 5936.27 9105.00 1504.27 6828.75 4552.50 7226.12 3262.65
Maintenance of ST MDRS Transferred from ZP(33+33 )& KRCRS 2225-02-277-0-37 5674.67 5942.00 11616.67 4456.50 2971.00 5087.33 3558.34
Starting of ST New MDRS(02 PU) 2225-02-277-0-34 1988.46 730.00 2718.46 547.50 547.50 1002.73 1533.23
EMRS Construction 2225-02-794-0-01 1487.50 0.00 1487.50 167.68 169.68 174.56 1482.62
EMRS Maintenance(04) 2225-02-794-0-01 743.95 0.00 1487.50 169.68 169.68 174.56 1482.62
Total 15830.85 15777.00 31607.85 13928.68 10166.93 14299.16 11698.62